Critical Sprinkler Irrigation Pump

Site Challenge

Polypump was approached by a leading irrigation contractor on the eve of the first wet test of the new sprinkler irrigation system installed at the Kingsholm Stadium home of Gloucester rugby club. The original supplier failed to deliver the required pump within the tight time frame required.

The project was in its final stages and all equipment needed to be installed & commissioned allowing time to test & refine the irrigation system prior to the start of the Premiership rugby season.

Site Solution

Working with the onsite contractor we gathered key information from the original specifation for the irrigation system. Polypump was now in a prime position to reselect, locate UK stock and deliver next day meaning all tests were able to go ahead without further delay.

Pump used was a Xylem Lowara e-SV 66SV 15kW. 

@ PolyPump Ltd 2024.
Registered VAT number is 826 0720 46    T&C Privacy Policy